Westmonte Renovation Update

If you've driven by Wesmonte Park lately, you may have noticed big changes. Here's the scoop on new developments:

  • New transformer and conduit for the main electrical feed are installed
  • Block walls on the administration building, outdoor pool, therapy pool and maintenance building are complete
  • Roof construction on all buildings is underway
  • Administration building interior blocking, studs and door frames along with ducts, fire sprinklers, electrical conduit and plumbing are installed

The next work phase will focus on:

  • Roofing and window installation
  • Metal building construction
  • Building interior wall construction
  • Block building exterior stucco and paint
  • Retaining wall construction

Last updated 10/4/2018